The largest bathroom in the house and the one worth getting right. A full gut and refit where the layout can actually change, run by one crew from demolition through to the last coat of paint.
Quick answer
A primary bath with mid-to-high finishes runs $28,000 to $60,000 and upwards, against $14,000 to $28,000 for a standard hall bathroom. Keeping the existing layout and refitting an en-suite sits around $22,000 to $38,000. Moving plumbing locations is the change that most reliably pushes a project past its first number.
The work
A primary bathroom is the one project where the room is big enough that the layout is a real decision rather than a constraint. There is usually space to move a shower, drop a bath, widen a vanity wall or steal a cupboard from the bedroom next door. That freedom is most of the value and all of the risk.
It is also the project where coordination stops being a convenience and becomes the thing you are actually buying. A full primary bath touches demolition, framing, plumbing, electrical, waterproofing, tile, glass, drywall, trim, paint and a stone top with a two-week lead time, and the order those arrive in is not negotiable. One trade a week late pushes everything behind it.
We run the construction scope ourselves and coordinate the licensed plumbing and electrical trades on one schedule, which is the honest version of what a general contractor sells. You get one point of contact, one programme and one person answering for the sequence, rather than four numbers and a group chat.
Maryland primary bathrooms. Selections move these totals far more than labour does, and moving plumbing locations is the one change that reliably adds thousands.
Ranges, not quotes. Real numbers come from a walkthrough — access, condition, height and finish level move a price more than square footage does. Estimates are free and in writing.
Get your numberFull primary baths cost guide for MarylandPrefer to just talk?
Call and describe the job. You’ll get a straight answer on whether it’s something we do and roughly what it runs.
(301) 524-1729
Self-performed
Primary bathroom remodel
What’s included
Written into the estimate, not assumed. If something on your job is not on this list, it gets priced and named before anyone starts.
What moves and what stays agreed on paper first, including the knock-on costs of relocating a soil stack or a shower drain, so nothing is discovered with the walls open.
Back to studs and subfloor with the room sealed, the route protected and the rest of the house kept out of it for five to eight weeks.
Walls corrected and squared, niches and benches framed, blocking set for glass, grab rails, wall-hung units and mirrors, and any new opening headed properly.
Plumbing and electrical performed by licensed trades and sequenced by us, with each rough-in inspected and signed off before anything closes over it.
The wet area built as one system to TCNA methods, flood tested, then tiled with the layout set out dry so the cuts land where they are least visible.
Drywall, trim, paint and the final fix done by the people who opened the room, so nothing waits on another contractor to come back and finish somebody else's work.
On the job
What the trade looks like at each stage. Photos of our own recent jobs come out at the walkthrough, on the actual house.




Straight answers
Not covered here? Call and ask — you’ll get a real answer, not a “depends on the job”.
Five to eight weeks from demolition to final walk, and we will not quote three. A large part of that is cure and lead time rather than labour: waterproofing cure, mortar and grout cure, paint, plus a stone top that is templated after the cabinets are in and takes a fortnight to come back. Compressing those is how a bathroom fails early.
Materially, yes. Keeping the drain and supply positions avoids opening the floor, avoids a ceiling repair below, and takes a chunk of licensed plumbing time out of the job. If the current layout works and you simply dislike the finishes, say so at the estimate and we will price the version that does not move anything.
For finishes alone, usually not. Once you are moving plumbing or electrical, altering structure or taking out a wall, you are into permit territory and inspections. We pull what the job needs and schedule around the inspection dates rather than working ahead of them and hoping.
Same crew, same visit
Most bathroom remodeling jobs are two or three of these at once, which is why they are priced and scheduled together rather than as separate call-outs.
From the field
Longer answers than a quote page has room for — how the work fails, what putting it right actually involves, and when waiting is the honest call.
Sources worth your time
None of these are ours. They are the offices and standards bodies that set the rules we work to, so you can verify what we say rather than take it.
Check any Maryland contractor's licence before you sign. Ours is on file with the Commission.
OpenThe county office that decides whether your job needs a permit. Routine gutter work does not; structural and roof work usually does.
OpenGermantown, Gaithersburg, Rockville and Clarksburg permits, which are their own process and their own timeline.
Open
Talk to the people doing the work
Tell us what needs doing. We’ll walk it with you, sequence every trade it touches, put the price in writing, and leave you to decide.
Get a quote
Two short steps. No obligation, no pressure — just a clear number and a straight answer about what the job involves.




Tick as many as you like. Most jobs are two or three of them at once, and I sort out the detail when I come and look. Nobody gets turned away for choosing the wrong box.