Drywall on new builds and additions across Central Maryland — stocked, hung and finished to a builder's schedule, with the rough-in inspections respected rather than worked around.
Quick answer
Hung and finished to level 4, new construction and addition work runs $1.85 to $3.10 per square foot of board in 2026, below our renovation rate because an empty shell is faster and cleaner than a lived-in house. A single-room addition with its ceiling typically lands at $2,400 to $6,000. Repetition brings it down, a cut-up custom plan with lots of short walls and soffits brings it up.
The work
On a new build or an addition, drywall is the hinge in the schedule. Everything before it is rough and parallel — framing, mechanical, electrical, plumbing, insulation, all of them able to work around each other. Everything after it is finish and sequential: trim, then paint, then floors, then fit-out, each one waiting on the last. A drywall crew that slips by a week slips the whole back half of the job.
So the thing a builder is actually buying is not board, it is a date. We quote the sequence as well as the price: when we stock, when we hang, how many days of finishing, and when the space is genuinely ready for the trim carpenter rather than nearly ready.
We also will not hang over an un-inspected rough-in, even when asked, and that is worth knowing before you call. Board over an electrical or framing rough-in that has not been signed off comes back off at somebody's cost, and the somebody is usually argued about afterwards. Where we are waiting on an inspection we will say so in writing on the day rather than at the end of the week.
Builder pricing by the square foot of board, quoted off the plan set and confirmed on a walk. Volume, repetition and a clear schedule all move this down; a cut-up custom plan moves it up.
Ranges, not quotes. Real numbers come from a walkthrough — access, condition, height and finish level move a price more than square footage does. Estimates are free and in writing.
Get your numberFull new construction cost guide for MarylandPrefer to just talk?
Call and describe the job. You’ll get a straight answer on whether it’s something we do and roughly what it runs.
(301) 524-1729
Self-performed
New construction and additions
What’s included
Written into the estimate, not assumed. If something on your job is not on this list, it gets priced and named before anyone starts.
Stocking, hanging and finishing days given as a sequence at quote stage, with the number of finishers it takes to hit them rather than an optimistic single-crew plan.
We hang after the inspections that have to precede it, and we flag in writing when we are held up rather than quietly boarding over the problem.
Board delivered and spread room by room, stacked where it does not load a single floor bay or block the trades still working behind us.
Fire-rated, moisture-resistant, abuse-resistant and sound board placed per your plan set, with any gap between the plan and the field raised before it is covered.
Level 4 as standard, level 5 where a dark paint or a long glazed wall demands it. Agreed at quote so nobody is arguing about it under a work light.
Scrap out, floors swept, dust pulled down off surfaces, and the openings cut. Trim carpenters should not be inheriting a clean-up.
On the job
What the trade looks like at each stage. Photos of our own recent jobs come out at the walkthrough, on the actual house.




Straight answers
Not covered here? Call and ask — you’ll get a real answer, not a “depends on the job”.
Hanging a single-room addition is usually a day, and finishing is the long pole: three coats with real drying time between them puts most additions at five to eight working days from stock to paint-ready. Humidity matters more than people expect — a damp week in July adds a day. We will not compress it by forcing dry mud, because that is where the cracked joints you see a year later come from.
No. We will stock, we will cut, and we will be ready to start the morning the sign-off lands, but board over an un-inspected framing, electrical or plumbing rough-in comes back off, and then the argument is about who pays. If a schedule is tight the right answer is to get the inspector earlier rather than to cover the work. We tell builders this at quote stage so it is not a surprise on site.
Yes, and a good share of our drywall volume is exactly that. What we ask for is the plan set, the board specification by room, and a realistic date; what you get is the sequence in writing and a crew sized to hold it. We also do hang-only where you have your own finishers, which is priced separately — see the hanging page for that.
Same crew, same visit
Most drywall jobs are two or three of these at once, which is why they are priced and scheduled together rather than as separate call-outs.
From the field
Longer answers than a quote page has room for — how the work fails, what putting it right actually involves, and when waiting is the honest call.
Sources worth your time
None of these are ours. They are the offices and standards bodies that set the rules we work to, so you can verify what we say rather than take it.
Check any Maryland contractor's licence before you sign. Ours is on file with the Commission.
OpenThe county office that decides whether your job needs a permit. Routine gutter work does not; structural and roof work usually does.
OpenWhere the residential-construction standards and material research behind these decisions are published.
Open
Talk to the people doing the work
Tell us what needs doing. We’ll walk it with you, sequence every trade it touches, put the price in writing, and leave you to decide.
Get a quote
Two short steps. No obligation, no pressure — just a clear number and a straight answer about what the job involves.




Tick as many as you like. Most jobs are two or three of them at once, and I sort out the detail when I come and look. Nobody gets turned away for choosing the wrong box.